However, it was announced that nearly three weeks into a state of expectation and uncertainty, and following its authorization, a decision has been reached by the Justice system on permits regarding resuming works on a major building project, specifically, on the Córdoba Lottery Hotel on the shores of a Cruz del Eje reservoir. The project was put on hold following approval of a collective injunction.
Suspension was initially ordered on December 29, when all construction activities ceased as an initial precautionary measure was instituted pending an injunction. The Comechingona Sanavirón Tulián Territorial Indigenous Community and its neighboring residents requested that construction activities be suspended and that the environmental license granted to the project be annulled.
Province Appeals and Escalates the Case
On receipt of this ruling, the Province of Córdoba presented an appeal of this order and asked that it be granted suspensory effects while it is being reviewed on appeal. However, this was denied by the Civil, Commercial, Labor, and Family Court of Appeals in Cruz del Eje, which prompted it to be taken to the Superior Court of Justice.
During the case in the highest court attended by the provincial government, the government pointed out to the court the damages to the economy incurred as a result of stopping the building project. They further noted the risks to the structures in the building due to the incomplete project. They pointed to the open trenches in the building project.
Superior Court Authorizes Continuation of Works
Finally, a decision was made in favor of proceeding, as ultimately decided by the Superior Court of Justice. The ruling emphasized that this project has a valid environmental license, which enjoys a presumption of legitimacy, as provided in administrative laws. Moreover, at this stage, there was a lack of evidence for a full stop of the project, as emphasized in the ruling.
Although the collective injunction based its arguments on the “precautionary principle” as established in Argentina’s General Environmental Law No. 25,675, which refers to environmental practices prior to the manifestation of serious or irreversible environmental damage, the court determined there had been no demonstration of actual environmental risk at this point.
Safety and Economic Considerations Weighed Heavily
The judges also considered the safety factors that could arise when the construction site remained abandoned. The presence of excavations and incomplete construction works was considered a real threat to public safety, thus justifying the decision to allow construction to resume under controlled circumstances.
This is not to say the court is dismissing these claims of environmental damage, but is simply allowing progress with this development while the dialogue continues. The Córdoba Lottery Hotel is back on with this ruling, and this is a major move in this debate concerning what is best for this area in terms of both environment and infrastructure.
Source: SBC Noticias